This study evaluated construction site erosion controls, finding compost erosion control blankets (CECBs) effective on steeper slopes. Results provide design guidance for effective stormwater management and sediment control.
Area of Science:
- Environmental Engineering
- Water Resource Management
- Soil Science
Background:
- National Pollutant Discharge Elimination System (NPDES) Phase II mandates erosion and sediment control best management practices (BMPs) for construction site stormwater management.
- Existing research lacks comprehensive data on the performance and optimal design of these critical BMPs.
Purpose of the Study:
- To comparatively evaluate the performance of common construction erosion control BMPs using a standardized test method.
- To assess the impact of compost erosion control blanket (CECB) thickness and slope angle on erosion control efficacy.
- To determine Universal Soil Loss Equation (USLE) cover management factors (C factors) for various BMPs to aid designers.
Main Methods:
- Twenty-three erosion control BMPs were tested using ASTM D-6459 on slopes of 4:1, 3:1, and 2:1 (H:V).
- Evaluations were conducted under simulated rainfall conditions of 5 cm and 10 cm.
- Soil loss reduction percentages and USLE C factors were calculated for each BMP treatment.
Main Results:
- Soil loss reduction varied significantly, ranging from -7% to 99% for 5 cm rainfall and 8% to 99% for 10 cm rainfall on a 2:1 slope.
- CECBs with 2.5 cm and 5 cm thickness effectively reduced erosion on slopes up to 2:1.
- CECBs less than 2.5 cm thick are not recommended for slopes of 4:1 or steeper with 5 cm rainfall.
Conclusions:
- Performance data and derived USLE C factors (0.01 to 0.9) offer valuable criteria for site planners and engineers.
- The study provides evidence-based guidance for selecting and designing effective erosion and sediment control BMPs.
- Optimized BMP selection can enhance stormwater pollution prevention plans and compliance with NPDES Phase II requirements.
More Related Videos
13:00Modifying the Bank Erosion Hazard Index (BEHI) Protocol for Rapid Assessment of Streambank Erosion in Northeastern Ohio
Published on: February 13, 2015
08:09Measuring and Mapping Patterns of Soil Erosion and Deposition Related to Soil Carbonate Concentrations Under Agricultural Management
Published on: September 12, 2017
Related Concept Videos
Design Example: Maintaining Level of an Embankment
Design Example: Managing Concrete Workability
To address...
Design Example: Analyzing Capacity Contours for Flood Risk Assessment
Conservation of Mass in Moving, Nondeforming Control Volume
In the context of a detention basin, the conservation of mass states that the total mass of water entering the basin must equal the mass leaving the basin plus any accumulation of...
Design Example: Sustainability in Concrete Building
There are multiple approaches to achieve sustainability in a commercial concrete building. For instance, construct a concrete parking area under the building, utilizing pervious concrete paver blocks in open areas to facilitate rainwater collection through an underground cistern.
Preplaced Aggregate Concrete