Falls from height during the floor slab formwork of buildings: current situation in Spain
Jose M Adam1, Francisco J Pallarés, Pedro A Calderón
1ICITECH, Departamento de Ingeniería de la Construcción y Proyectos de Ingeniería Civil, Universidad Politécnica de Valencia, Camino de Vera s/n, 46071 Valencia, Spain. joadmar@cst.upv.es
Problem:
One of the phases with the highest risk of falls from a height in the construction of a building is during the floor slab formwork stage. This paper analyzes this particular risk, as well as the most frequently used fall-protection systems.
Method:
A survey was carried out to define the current situation in Spain with regard to falls from a height during floor slab formwork and the fall-protection systems used to prevent such a risk.
Results:
The results of the survey clarified the current situation in Spain with regard to this risk, and made it clear that there is considerable risk of falling from a height during the floor slab formwork stage.
Discussion:
All the safety systems analyzed presented a series of weak points that should be studied in detail before they can be used on building sites.
Impact On Industry:
The risk of falling associated with floor slab formwork and the most frequently used protection systems are analyzed. As no research had been carried out to date on this type of risk, we consider the research presented in this article to be a pioneer in the field.
Related Concept Videos
Shrinkage in Concrete
When concrete is still in its plastic state, it can undergo a decrease in volume by about 1% of its absolute volume. This decrease is known as plastic shrinkage. It arises either...
Effects of Creep
Prestressed Concrete
Posttensioned Masonry Walls
Post-tensioned masonry walls use high-strength steel rods or flexible tendons to enhance the strength and efficiency of masonry structures. These elements are securely anchored to the foundation and extend vertically either within the cores of the masonry units or between the masonry wythes. The construction process involves building the wall with these tensioning elements in place and allowing the mortar to fully cure.
Following the curing process, the tensioning begins. Steel rods are...
Slump Test
Concrete is poured into the mold in three layers to conduct the test. Each layer is compacted 25 times with a steel tamping rod, which has a five-eighths-inch diameter and a rounded end, to ensure even distribution and eliminate...
Reinforced Brick Masonry
To fortify brick walls...