Combining Monte Carlo Simulation and Bayesian Networks Methods for Assessing Completion Time of Projects under Risk
Ali Namazian1, Siamak Haji Yakhchali1, Vahidreza Yousefi2
1Department of Industrial Engineering, College of Engineering, University of Tehran, Tehran 1417414418, Iran.
This study introduces a new risk assessment framework for construction projects, combining Monte Carlo simulation and Bayesian networks. It helps manage project risks and their combined impact on completion time.
Area of Science:
- Construction Management
- Risk Analysis
- Project Management
Background:
- Construction projects frequently face risks impacting timely and budget-conscious completion.
- Project success hinges on effective risk control and understanding risk interactions.
- Existing models often neglect the aggregated impact and amplification of interacting risks.
Purpose of the Study:
- To develop a novel structure for assessing the aggregated impact of construction project risks on completion time.
- To address the limitations of current models in estimating the combined and intensifying effects of risks.
- To provide a validated framework for proactive risk management in construction.
Main Methods:
- Integration of Monte Carlo simulation and Bayesian network methodologies.
- Development of a risk assessment structure accounting for inter-risk dependencies.
- Application and validation of the proposed model through an industrial case study.
Main Results:
- The developed structure provides an indicator for estimating the aggregated impact of risks, considering their interactions.
- The case study validated the model's functionality and demonstrated its implementation procedure.
- The study highlights the importance of assessing intensified risk impacts in construction projects.
Conclusions:
- The proposed structure enhances the assessment of aggregated risk impacts on construction project timelines.
- Effective management of interacting risks is crucial for improving project success rates.
- The integrated simulation and network approach offers a robust tool for construction risk management.
Related Concept Videos
Hazard Rate
Kaplan-Meier Approach
Uncertainty: Confidence Intervals
Design Example: Analyzing Capacity Contours for Flood Risk Assessment
Decision Making: P-value Method
First, a specific claim about the population parameter is proposed. The claim is based on the research question and is stated in a simple form. Further, an opposing statement to the claim is also stated. These statements can act as null and alternative hypotheses: a null hypothesis would be a neutral statement while the alternative hypothesis can...
Propagation of Uncertainty from Systematic Error