Combining Monte Carlo Simulation and Bayesian Networks Methods for Assessing Completion Time of Projects under Risk

Ali Namazian1, Siamak Haji Yakhchali1, Vahidreza Yousefi2

  • 1Department of Industrial Engineering, College of Engineering, University of Tehran, Tehran 1417414418, Iran.

Summary

This study introduces a new risk assessment framework for construction projects, combining Monte Carlo simulation and Bayesian networks. It helps manage project risks and their combined impact on completion time.

Related Concept Videos

Hazard Rate01:11

Hazard Rate

The hazard rate, also known as the hazard function or failure rate, is a statistical measure used to describe the instantaneous rate at which an event occurs, given that the event has not yet happened. From a probabilistic perspective, it represents the likelihood that a subject will experience the event in a very small time interval, conditional on surviving up to the beginning of that interval. In terms of frequency, the hazard rate can be viewed as the ratio of the number of events to the...
367
Kaplan-Meier Approach01:24

Kaplan-Meier Approach

The Kaplan-Meier estimator is a non-parametric method used to estimate the survival function from time-to-event data. In medical research, it is frequently employed to measure the proportion of patients surviving for a certain period after treatment. This estimator is fundamental in analyzing time-to-event data, making it indispensable in clinical trials, epidemiological studies, and reliability engineering. By estimating survival probabilities, researchers can evaluate treatment effectiveness,...
516
Uncertainty: Confidence Intervals00:54

Uncertainty: Confidence Intervals

The confidence interval is the range of values around the mean that contains the true mean. It is expressed as a probability percentage. The interpretation of a 95% confidence interval, for instance, is that the statistician is 95% confident that the true mean falls within the interval. The upper and lower limits of this range are known as confidence limits. The confidence limits for the true mean are estimated from the sample's mean, the standard deviation, and the statistical factor...
10.0K
Design Example: Analyzing Capacity Contours for Flood Risk Assessment01:17

Design Example: Analyzing Capacity Contours for Flood Risk Assessment

Flood risk assessment involves careful planning and analysis to ensure the safety of communities near water retention structures. Capacity contours are a vital tool in this process, as they illustrate the potential spread of water at specific levels in a given area. In the context of building a bund across a small valley, these contours play a critical role in evaluating the safety of nearby residential areas.In this example, the bund is intended to store stormwater in the valley. The engineers...
254
Decision Making: P-value Method01:09

Decision Making: P-value Method

The process of hypothesis testing based on the P-value method includes calculating the P- value using the sample data and interpreting it.
First, a specific claim about the population parameter is proposed. The claim is based on the research question and is stated in a simple form. Further, an opposing statement to the claim  is also stated. These statements can act as null and alternative hypotheses:  a null hypothesis would be a neutral statement while the alternative hypothesis can...
6.8K
Propagation of Uncertainty from Systematic Error01:10

Propagation of Uncertainty from Systematic Error

The atomic mass of an element varies due to the relative ratio of its isotopes. A sample's relative proportion of oxygen isotopes influences its average atomic mass. For instance, if we were to measure the atomic mass of oxygen from a sample, the mass would be a weighted average of the isotopic masses of oxygen in that sample. Since a single sample is not likely to perfectly reflect the true atomic mass of oxygen for all the molecules of oxygen on Earth, the mass we obtain from this...
1.2K