A construction project scheduling methodology considering COVID-19 pandemic measures
Related Experiment Video
Updated: Oct 1, 2025

Nasal Brushing Sampling and Processing Using Digital High Speed Ciliary Videomicroscopy – Adaptation for the COVID-19 Pandemic
Published on: November 7, 2020
Selman Aslan1, Osman Hürol Türkakın2
1Department of Transportation Services, Muş Alparslan University, Turkey.
Introduction:
At the beginning of the COVID-19 pandemic, various social measures were taken and various sectors were affected with strict precautions and safety measurements. The construction industry, where numerous employees work together, was affected by these COVID restrictions. The pandemic period typically further delayed the construction contracts.
Methods:
This study addresses the project duration, pandemic risk, and project cost of a construction project case by using both multi-objective genetic algorithm and resource constrained project scheduling techniques, using modeling of COVID-19 infection rate. Finally, the analytic hierarchy process (AHP), a multi-objective technique, is used to obtain an optimal solution using three criteria: project duration, total cost, and pandemic risk value.
Results:
A case study is used for analyzing the outcomes of the pandemic-based modeling, the original schedule of the case study ends in 46 days. Feasible schedules are obtained with durations occurring between 61 to 199 days, the pandemic risks range from 46% to 89%, and the total cost varies from 174,669.8 Turkish Lira (TL) to 186,126.7 TL. Consequently, the most optimal-final solution is obtained Alternative 5 (0.46% pandemic risk, 199 Day (10 workers) with 185,722 TL).
Conclusion:
We conclude that the possible rate of pandemic-related delays can be obtained by using both these techniques and the infection modeling method. Using the COVID-19 infection rate modeling, duration and cost changes are calculated by considering infection risk in construction workers. Practical Applications: Using the COVID-19 infection rate modeling, project delays and cost overruns are determined by considering infection risk in construction workers. Optimum worker sizes and delayed construction activities are determined according to the selected solution by using the AHP technique. Expectedly, this study may help determine the construction process while preserving social distances between construction workers during pandemic situations like COVID-19.
Related Concept Videos
Steps in Outbreak Investigation
Design Example: Dimensioning of Concrete Masonry Construction
The site engineer has laid out a plan for the storeroom with external dimensions of twelve feet in length and...
Design Example: Managing Concrete Workability
Design Example: Sustainability in Concrete Building
There are multiple approaches to achieve sustainability in a commercial concrete building. For instance, construct a concrete parking area under the building, utilizing pervious concrete paver blocks in open areas to facilitate rainwater collection through an underground...
Preplaced Aggregate Concrete
Aggregate Cement Ratio

