Instance dataset for resource-constrained project scheduling with diverging material flows
Marco Gehring1, Rebekka Volk1, Frank Schultmann1
1Karlsruhe Institute of Technology, Institute for Industrial Production (IIP), Hertzstr. 16, 76187 Karlsruhe, Germany.
This data article introduces a dataset for the resource-constrained project scheduling problem with cumulative resources (RCPSP/c), crucial for projects like nuclear dismantling. It offers 192 instances and benchmark solutions to advance scheduling method research.
Area of Science:
- Operations Research
- Computer Science
- Engineering Management
Background:
- Project scheduling with diverging material flows presents challenges due to limited processing and storage capacities.
- Nuclear dismantling and deconstruction projects exemplify scenarios with complex material management requirements.
- Existing scheduling models may not fully capture the intricacies of cumulative resource constraints.
Purpose of the Study:
- To introduce a novel dataset for the resource-constrained project scheduling problem with cumulative resources (RCPSP/c).
- To provide a benchmark for evaluating and developing new solution methods for RCPSP/c.
- To facilitate research on scheduling problems involving resource production and consumption.
Main Methods:
- Mathematical formulation of the problem as a resource-constrained project scheduling problem with cumulative resources (RCPSP/c).
- Generation of 192 artificial instances with varying complexities.
- Computation of heuristic solutions for each instance, including different objective function variants.
Main Results:
- A comprehensive dataset of 192 RCPSP/c instances is now available.
- Heuristic solutions and modeling variants are provided for each instance.
- The dataset enables comparative analysis of scheduling algorithms.
Conclusions:
- The dataset serves as a valuable benchmark for the RCPSP/c.
- It supports the evaluation of heuristic and exact methods for complex project scheduling.
- Facilitates advancements in scheduling for industrial deconstruction and material flow management.
More Related Videos
Related Concept Videos
Design Example: Managing Concrete Workability
Cluster Sampling Method
To choose a cluster sample, divide the population into clusters (groups) and then randomly select some of the clusters. All the members from these clusters are in the cluster sample. For example, if you randomly sample four departments from your...
Design Example: Aggregate Gradation
The grading, or particle-size distribution, of sand is determined using sieve analysis, with standard sizes ranging from 150 μm to 10 mm (ASTM No. 100 sieve to 3⁄8 in. sieve). Sand is...
Distributed Loads: Problem Solving
Design Example: Analyzing Capacity Contours for Flood Risk Assessment
Rapidly Varying Flow