Model (At Least) Twice, Build Once: Experiences With the Design-Bid-Build Process for Solar Photovoltaic Arrays.
Brian Dougherty1, Matthew Boyd1
1National Institute of Standards and Technology, 100 Bureau Drive, Stop 8632, Gaithersburg, MD 20899-8632.
Summary
Independent modeling of solar photovoltaic (PV) systems improved contractor designs, leading to an estimated 2.5% increase in annual energy generation for commercial-scale arrays. This study details the process and outcomes.
Area of Science:
- Engineering
- Renewable Energy Systems
Background:
- Commercial-scale solar photovoltaic (PV) arrays were installed at the National Institute of Standards and Technology (NIST) campus.
- A design-bid-build process was utilized, involving contractor use of PV system modeling tools.
Purpose of the Study:
- To conduct independent PV system modeling to identify design improvements.
- To maximize annual renewable energy generation from the installed PV arrays.
Main Methods:
- Independent photovoltaic system modeling was performed to analyze contractor designs.
- Key events impacting the design-bid-build process were documented.
- Installed systems were summarized and compared with proposed designs.
Main Results:
- Independent modeling identified design elements for improvement.
- An estimated 2.5% gain in annual energy generation was achieved.
- Power generation data from three sites over two 12-month intervals were compared.
Conclusions:
- Independent modeling is a valuable tool for optimizing PV system design and maximizing energy output.
- The study provides insights into the design-bid-build process for large-scale renewable energy projects.
More Related Videos
Related Concept Videos
Design of Prismatic Beams for Bending
The design of prismatic beams, structural elements with a uniform cross-section, focuses on ensuring safety and structural integrity under load. The design process begins by determining the allowable stress, either from material properties tables, or by dividing the material's ultimate strength by a safety factor. This safety factor is essential for accommodating uncertainties, and varies depending on the material—timber, steel, or concrete—with each having unique strength and stress...
Wind Turbine Machine Models
In the growing field of wind energy, incorporating wind turbine models into transient stability analysis is essential. Induction and synchronous machines are the primary models used, with induction machines being prevalent due to their simplicity and reliability.
Induction machines interact through the rotating magnetic field generated by the stator and the rotor. The key parameter is slip, which is the difference between synchronous speed and rotor speed relative to synchronous speed. Slip is...
Induction machines interact through the rotating magnetic field generated by the stator and the rotor. The key parameter is slip, which is the difference between synchronous speed and rotor speed relative to synchronous speed. Slip is...
Design Example: Sustainability in Concrete Building
As the construction industry moves towards more eco-friendly practices, concrete's adaptability and its ability to incorporate sustainable features make it a key material in the drive towards greener building solutions.
There are multiple approaches to achieve sustainability in a commercial concrete building. For instance, construct a concrete parking area under the building, utilizing pervious concrete paver blocks in open areas to facilitate rainwater collection through an underground cistern.
There are multiple approaches to achieve sustainability in a commercial concrete building. For instance, construct a concrete parking area under the building, utilizing pervious concrete paver blocks in open areas to facilitate rainwater collection through an underground cistern.