概括
巴基斯坦 巴基斯坦 巴基斯坦.
科学领域:
- 电气工程 电气工程
- 计算机科学 计算机科学
- 环境科学 环境科学
背景情况:
- 巴基斯坦面临着日益增长的能源需求和环境问题,需要向更智能,更绿色的能源基础设施过渡.
- 为了应对这些挑战,Gujranwala电力公司 (GEPCO) 正在实施实时 (RT) 智能计量网络.
- 目前的能源基础设施需要现代化,以提高效率和环境可持续性.
研究的目的:
- 介绍巴基斯坦实时智能计量网络部署的实际应用和结果.
- 评估基于物联网 (IoT) 架构的智能能源系统的有效性.
- 展示智能计量对电网可见性,运营响应性和需求侧管理的好处.
主要方法:
- 设计和实施了一个四层物联网架构,包括能源监控,通信,云分析和应用层.
- 在工业负载类别中部署了智能电表 (SM),以实时传输电气参数 (电压,电流,功率因子,频率,消耗).
- 数据被发送到一个集中式计量器数据管理系统 (MDMS),用于自动计费,负载分析,故障检测和电力质量分析.
主要成果:
- 智能计量系统使实时监控成为可能,提高了电网可见性和运营响应性.
- 识别低功率因子 (PF) 情况导致电容器银行部署,从而节省了大量的能源和成本.
- 该系统成功检测了电压失衡,频率变化和每日峰值负载模式,改进了电源质量分析.
结论:
- 支持物联网的智能计量网络是巴基斯坦需求侧管理 (DSM),损失减少和电网优化的实用工具.
- 该研究为寻求现代化能源系统的发展中国家提供了可复制的框架.
- 概述了大规模智能电网 (SG) 实施的关键技术推动因素,政策考虑因素和机构要求.
相关概念视频
Electrical Power
Electric power is the product of current and voltage, represented in units of joules per second, or watts. For example, cars often have one or more auxiliary power outlets with which you can charge a cell phone or other electronic devices. These outlets may be rated at 20 amps and 12 volts, so that the circuit can deliver a maximum power of 240 watts. Consider a 25 Watt bulb and a 60 Watt bulb. The conversion of electrical energy produces heat and light, while the kinetic energy lost by the...
Distributed Loads
Distributed loads are a common type of load that engineers and scientists encounter in various practical situations. Distributed loads often refer to a type of load spread over a surface or a structure and can be modeled as continuous force per unit area.
For example, consider a bookshelf filled with books stacked vertically adjacent to each other. The weight of the books is evenly distributed over the length of the shelf. As a result, the pressure at different locations on the surface of the...
For example, consider a bookshelf filled with books stacked vertically adjacent to each other. The weight of the books is evenly distributed over the length of the shelf. As a result, the pressure at different locations on the surface of the...
Distributed Loads: Problem Solving
Beams are structural elements commonly employed in engineering applications requiring different load-carrying capacities. The first step in analyzing a beam under a distributed load is to simplify the problem by dividing the load into smaller regions, which allows one to consider each region separately and calculate the magnitude of the equivalent resultant load acting on each portion of the beam. The magnitude of the equivalent resultant load for each region can be determined by calculating...
Power System Distribution
Power system distribution involves delivering electrical energy from power plants to consumers through a network of transmission and distribution systems. The process begins at power plants, where energy from coal, gas, nuclear, water, and wind is converted into electrical energy. These plants use three-phase generators, typically rated between 50 to 1300 MVA, with terminal voltages ranging from a few kV to 20 kV, depending on the size and age of the units.
The transmission system is designed...
The transmission system is designed...
Transformers in Distribution System
Transformers in distribution systems can be broadly categorized into distribution substation transformers and other distribution transformers. They are crucial for stepping down high transmission voltages to levels suitable for distribution and end-user applications.
Distribution substation transformers come in various ratings and typically use mineral oil for insulation and cooling. To prevent moisture and air from entering the oil, some transformers use an inert gas like nitrogen to fill the...
Distribution substation transformers come in various ratings and typically use mineral oil for insulation and cooling. To prevent moisture and air from entering the oil, some transformers use an inert gas like nitrogen to fill the...
Maximum Power Flow and Line Loadability
The maximum power flow for lossy transmission lines is derived using ABCD parameters in phasor form. These parameters create a matrix relationship between the sending-end and receiving-end voltages and currents, allowing the determination of the receiving-end current. This relationship facilitates calculating the complex power delivered to the receiving end, from which real and reactive power components are derived.