Safety inspections in construction sites: A systems thinking perspective.
1DEPROT/UFRGS (Industrial Engineering and Transportation Department, Federal University of Rio Grande do Sul), Av. Osvaldo Aranha, 99, 5. Andar, Porto Alegre, RS, CEP 90035-190, Brazil.
Accident; Analysis and Prevention
|November 12, 2015
Summary
Systems thinking (ST) offers valuable insights into construction safety inspections. Applying ST principles to study design and data analysis enhances understanding of inspection processes and outcomes.
Area of Science:
- Occupational Health and Safety
- Systems Engineering
- Construction Management
Background:
- Government safety inspections are crucial for accident prevention in construction.
- There is a lack of in-depth understanding regarding the processes and outcomes of these safety inspections.
- Existing research has not fully explored the application of systems thinking to analyze safety inspection effectiveness.
Purpose of the Study:
- To address the knowledge gap concerning the outcomes and processes of government safety inspections in construction.
- To apply systems thinking (ST) as a framework for gaining deeper insights into safety inspections.
- To explore how specific attributes of ST can be utilized within the context of construction site safety inspections.
Main Methods:
- Conducted thirteen case studies of construction sites with prohibited works over a six-year period.
- Employed a qualitative research approach integrating participant observation, direct observations, document analysis, and interviews.
- Utilized four key attributes of systems thinking to analyze the inspection processes within the case studies.
Main Results:
- Identified two complementary approaches for gaining insights into safety inspections using ST.
- Demonstrated that the study design itself must align with ST principles for effective analysis.
- Highlighted the importance of focusing data collection and analysis on agents, their interactions, constraints, opportunities, and outcomes.
Conclusions:
- Systems thinking provides a robust lens for understanding the complexities of construction safety inspections.
- Effective safety inspection analysis requires an ST-informed study design and a focus on systemic interactions.
- Recommendations for improving safety inspections can be derived by analyzing agent interactions and influencing factors within the system.
Related Concept Videos
Survey Safety
466
Surveying near highways, rough terrain, or power lines involves significant risks. Working along highways is particularly dangerous and requires the use of warning signs and flagmen. It is safest to avoid working directly on roads and use offsets whenever possible. When highway work is unavoidable, it must follow all safety guidelines. Surveyors should wear bright clothing, such as orange reflective vests, to ensure visibility to motorists, coworkers, and hunters. In construction zones, wearing...
466
Design Consideration
634
Designing a structure involves a series of considerations, primarily the material's ultimate strength, calculated through tests that measure changes under increased force until the material reaches its breaking point or limit. The ultimate load, where the material breaks, is divided by its original cross-sectional area, resulting in the ultimate normal stress or strength. The ultimate shearing stress is another significant factor taken into account.
The factor of safety is another key...
The factor of safety is another key...
634
Design Example: Managing Concrete Workability
333
This example deals with managing the workability of concrete for a raft foundation project under hot weather conditions. Workability is crucial for ensuring the concrete is easy to place, compact, and finish. In this scenario, a slump test — a common method to measure the workability of fresh concrete — initially indicated low workability. This was attributed to the rapid water loss from the concrete mix, exacerbated by the high temperatures causing the course aggregates to heat up.
333
Household Wiring And Electrical Safety
2.0K
Companies that supply power to most modern households use three conductors, typically called a three-wire line. While one is neutral, the other two are both at 120 V but with opposite polarity, giving a voltage of 240 V between them. With a three-wire line, high-power appliances that require 240 V, such as electric stoves and clothes dryers, are linked between the two hot lines. 120 V appliances can be connected between the neutral and either of the hot lines. The neutral side, which is always...
2.0K
Schemas
12.5K
A schema is a mental construct consisting of a cluster or collection of related concepts (Bartlett, 1932). There are many different types of schemata, and they all have one thing in common: schemata are a method of organizing information that allows the brain to work more efficiently. When a schema is activated, the brain makes immediate assumptions about the person or object being observed.
12.5K
Machines: Problem Solving II
745
Machines are complex structures consisting of movable, pin-connected multi-force members that work together to transmit forces. Consider a lifting tong carrying a 100 kg load. It comprises movable sections DAF and CBG linked together with member AB.
745