Lagged settlement in sandy cobble strata and earth pressure on shield tunnel
Ji Zhi Huang1, Yong Zhang2,3,4, Xiao Wei Ouyang5
1School of Civil Engineering & Transportation, South China University of Technology, Guangzhou, Guangdong 510641, China.
Abstract:
Lagged settlement is a typical accident induced by shield construction in sandy cobble strata. This paper analyzed the process and mechanism of lagged settlement, results show that all phases are in accord with the characteristics of ellipsoid theory of particle flows. Based on this theory, a method for calculating coefficient of lateral earth pressure and loosened earth pressure is proposed in this research. For the coefficient of lateral earth pressure, the boundary of loosened ellipsoid is divided into two parts, the arch zone and the excavation zone, and the lateral pressure coefficients are derived respectively according to the stress state. For loosened earth pressure on tunnel, the Terzaghi earth pressure theory and Protodyakonov earth pressure theory are adapted in different conditions according to the state of loosened cobble soil. Theories developed in this study can be applied on determination of shield excavation parameters, as well as calculation of loosened earth pressure and control of tunnel support.
Related Concept Videos
Transition Zone
Unsoundness of Aggregate due to Volume Change
Deleterious Substances in Aggregate
Another type of impurity is clay and fine material that...
Preplaced Aggregate Concrete
Design Example: Maintaining Level of an Embankment
Mortar Joint Deterioration in Masonry
The...