Simulation based scheduling of crew routing with learning and forgetting effects in repetitive projects
Tayseir Hegazy1,2, Khaled Hamdy3, Hatem El-Behairy3
1Department of Structural Engineering, Ain Shams University (ASU), Cairo, Egypt. Tayhegazy@aucegypt.edu.
Scientific Reports
|February 28, 2025
Summary
The Line of Balance (LOB) technique optimizes repetitive project scheduling. Balancing distinct crews versus routed crews impacts project duration and crew numbers, with simulation offering a solution.
Area of Science:
- Construction Management
- Operations Research
Background:
- The Line of Balance (LOB) is a scheduling technique for repetitive projects.
- It offers advantages over Critical Path Method (CPM) by promoting workflow consistency and leveraging the learning rate effect.
- The learning rate effect shortens activity durations as crews repeat tasks.
Purpose of the Study:
- To investigate the trade-offs between maintaining dedicated crews for each activity and implementing crew routing in repetitive projects.
- To analyze the impact of crew assignment strategies on project duration and the total number of crews required.
- To explore a simulation-based approach for optimizing crew numbers and movement in LOB scheduling.
Main Methods:
- Comparative analysis of two crew assignment strategies: dedicated crews per activity versus routed crews.
- Evaluation of the learning rate effect on activity durations with consistent crew assignments.
- Development and application of a simulation model to optimize crew allocation and routing.
Main Results:
- Dedicated crew assignments minimize project duration but necessitate a larger number of crews.
- Crew routing reduces the total number of crews but leads to an increase in overall project duration.
- A simulation approach can effectively balance crew numbers and project duration.
Conclusions:
- Optimizing crew assignments in LOB scheduling involves a trade-off between project duration and resource utilization (number of crews).
- Crew routing can be cost-effective by reducing indirect costs, despite potentially increasing project duration.
- A project-specific simulation model is crucial for optimizing crew numbers and routing decisions in repetitive construction projects.
Keywords:
Construction managementDelay risk assessmentLine-of-balance (LOB) schedulingRepetitive projectsMore Related Videos
Related Concept Videos
Reinforcement Schedules
126
Positive reinforcement is a powerful method for teaching new behaviors to both animals and humans. B.F. Skinner demonstrated this with his experiments using rats in a Skinner box. When a rat pressed a lever, it received a food pellet. This immediate reward encouraged the rat to repeat the behavior. This method, where a reward follows every instance of the behavior, is known as continuous reinforcement. It is highly effective for establishing new behaviors quickly.
Once a behavior is learned,...
Once a behavior is learned,...
126
Mechanistic Models: Compartment Models in Algorithms for Numerical Problem Solving
38
Mechanistic models play a crucial role in algorithms for numerical problem-solving, particularly in nonlinear mixed effects modeling (NMEM). These models aim to minimize specific objective functions by evaluating various parameter estimates, leading to the development of systematic algorithms. In some cases, linearization techniques approximate the model using linear equations.
In individual population analyses, different algorithms are employed, such as Cauchy's method, which uses a...
In individual population analyses, different algorithms are employed, such as Cauchy's method, which uses a...
38
Stereotype Content Model
13.9K
The Stereotype Content Model (SCM) was first proposed by Susan Fiske and her colleagues (Fiske, Cuddy, Glick & Xu, 2002; see also Fiske, 2012 and Fiske, 2017). The SCM specifies that when someone encounters a new group, they will stereotype them based on two metrics: warmth—or that group’s perceived intent, and how likely they are to provide help or inflict harm—and competence—or their ability to carry out that objective. Depending on the warmth-competence...
13.9K