Evaluation of construction progress of smart highway: a Bayesian network model
Chao Wang1, Haining Wang2, Shang Liu1
1Shandong Provincial Communications Planning and Design Institute Group Co. Ltd, Ji'nan, 250101, China.
Scientific Reports
|May 22, 2026
Summary
Accurate progress control for intelligent highways requires a new framework. This study introduces a multi-dimensional system combining expert and quantitative evaluation for better project management and decision-making.
Area of Science:
- Construction Management
- Intelligent Transportation Systems
- Project Monitoring
Background:
- Traditional progress evaluation methods are insufficient for intelligent highway construction due to complex integration of digital technologies and electromechanical equipment.
- Intelligent highway projects present unique challenges in progress assessment stemming from technological complexity and intricate construction interfaces.
- Effective progress control is critical for the successful and timely completion of advanced infrastructure projects.
Purpose of the Study:
- To develop and validate a novel progress evaluation framework specifically designed for intelligent highway construction projects.
- To establish a multi-dimensional indicator system that captures both schedule performance and technology-specific characteristics.
- To provide a practical tool for enhancing the precision and adaptability of intelligent highway construction management.
Main Methods:
- Analysis of project progress factors and construction management requirements.
- Development of a multi-dimensional indicator system integrating schedule and technological aspects.
- Combination of expert judgment with quantitative evaluation methods.
- Application and validation using real-world data from an intelligent highway construction case study.
Main Results:
- The proposed framework effectively reflects the actual progress status of intelligent highway construction stages.
- Key factors influencing schedule deviations were identified through case study application.
- The method provides actionable insights for project managers to make timely corrective decisions.
- Demonstrated superiority over conventional methods in accounting for technological complexity.
Conclusions:
- The developed framework offers a practical and effective solution for progress monitoring in intelligent highway construction.
- It enhances the precision and adaptability of construction management for technologically advanced projects.
- The study contributes to improving project control and decision-making in complex infrastructure development.
- The findings support the adoption of tailored evaluation methods for specialized construction environments.
Related Concept Videos
Design Example: Alignment of a Road Line Using GIS
The alignment of a road line using Geographic Information Systems (GIS) is a critical process in civil engineering, combining advanced technology with practical decision-making. This methodology begins with the collection of geospatial data, including information on land cover, geomorphology, drainage patterns, slope, and contour details. Such data is typically acquired through satellite imagery and GIS tools, offering a comprehensive understanding of the terrain.Once the data is gathered, it...
Design Example: Analyzing Capacity Contours for Flood Risk Assessment
Flood risk assessment involves careful planning and analysis to ensure the safety of communities near water retention structures. Capacity contours are a vital tool in this process, as they illustrate the potential spread of water at specific levels in a given area. In the context of building a bund across a small valley, these contours play a critical role in evaluating the safety of nearby residential areas.In this example, the bund is intended to store stormwater in the valley. The engineers...